Field station renewal
Alder Works · Facilities Operations · Q-2048. Draft pricing. Issued 20 November 2026. Valid through 20 December 2026.
Order summary
USD 10,670.00 one time and 120.00 monthly. The optional 450.00 inspection requires separate approval.
Scope of work
Atlas station · At each receiving bay, capture the equipment reading before dispatch.
Harbor reserve · Keep one station online while the site supply is being serviced.
| When | Owner | Phase | Acceptance check |
|---|---|---|---|
| Week 1 | Facilities lead | Site survey | Site access, power and mounting positions confirmed. |
| Weeks 2–3 | Field engineering | Installation | Each station commissioned against the equipment list. |
| Week 4 | Operations sponsor | Acceptance | Training and handoff checklist acknowledged. |
Configured pricing
Atlas station
| Component and SKU | Qty | List each | Discount | Net |
|---|---|---|---|---|
| Field station with sealed enclosure · AT-210 | 2 | 3,125.00 | 12% | 5,500.00 |
| Mount and cable harness · AT-041 | 2 | 95.00 | 0% | 190.00 |
| Commissioning and operator training · SV-106 | 1 | 850.00 | 0% | 850.00 |
Bundle subtotal 6,540.00 USD. Monthly support 60.00 USD.
Harbor reserve
| Component and SKU | Qty | List each | Discount | Net |
|---|---|---|---|---|
| Power cabinet with changeover relay · HB-310 | 1 | 3,750.00 | 8% | 3,450.00 |
| Reserve battery module · HB-014 | 2 | 340.00 | 0% | 680.00 |
Bundle subtotal 4,130.00 USD. Monthly support 60.00 USD.
Optional service · Annual on-site readiness inspection · 450.00 USD.
Commercial terms
| Milestone | Share | Amount |
|---|---|---|
| At order | 30% | 3,201.00 |
| After commissioning | 40% | 4,268.00 |
| On acceptance | 30% | 3,201.00 |